Thank you to all who attended the Ribbon Cutting Ceremony for the two new Career Technical Education Buildings to be open mid-June.
More pictures can be found at: http://gallery.imperial.edu/CTE-Buildings-Ribbon-Cutting-Ceremony
Thank you to all who attended the Ribbon Cutting Ceremony for the two new Career Technical Education Buildings to be open mid-June.
More pictures can be found at: http://gallery.imperial.edu/CTE-Buildings-Ribbon-Cutting-Ceremony
All bond funds have been expended. The next Citizens Bond Oversight Committee meeting is TBA.
Construction for the Career Technical Facilities project continues and is approximately 81% complete!
November 2013 Progress Update
Work Completed
Building 3100: Work completed for this month included the fire sprinkler installation, HVAC rough-in (above ceilings) wet and dry, and hangin drywall walls and ceilings
Building 3200: Work completed for this month included the aluminum interior storefronts installation and tape/texturing walls and ceilings
Work in Progress
Building 3100: Work in progress includes the aluminum storefronts installation, storefront glazing, and taping/texturing walls
Building 3200: Work in progress includes the storefront glazing and paint interior walls and ceiling
Site: Work in progress includes concrete work – grade, form, rebar, and pour
Upcoming Work
Building 3100: Upcoming work includes the painting of the interior walls and ceilings
Building 3200: Upcoming work includes ceramic tile at the toilet rooms, T-bar ceiling grid work, display cases at entrances, cabinets and millwork, electrical ceiling fixtures and trim, mechanical ceiling fixtures, plumbing fixtures and finishes, and miscallenous exterior finishes
Site: Upcoming work includes the mechanical equipment and piping installation, asphalt paving of the road, and sleeves for irrigation under concrete
Construction for the Career Technical Facilities project continues and is approximately 63% complete!
August 2013 Progress Update
Work Completed
Building 3100: Work completed for this month included steel framing roof equipment, metal roof decking, MEP sleeves through roof and hangers, tubular skylight curbs installation, frame interior walls, and exterior sealer
Building 3200: Work completed for this month included the metal decking at the roof, MEP sleeves through roof and hangers, fire sprinkler installation, MEP wall and soffit rough-in
Site: Work completed for this month included the structural steel for shade structures
Work In Progress
Building 3100: Work in progress includes installing the roof drains, fire sprinkler installation, hollow metal door frames installation, MEP rough-in at walls and soffit, and ceilings and soffit framing
Building 3200: Work in progress includes setting mechanical curbs at roof, exterior window installation and glazing, HVAC rough-in above ceiling – wet and dry, and electrical rough-in above ceiling
Upcoming Work
Building 3100: Upcoming work includes setting mechanical curbs at roof, roof hatches and accessories, PVC membrane roofing, sheet metal flashings, exterior windows installation and glazing, and set HVAC roof equipment
Building 3200: Upcoming work includes roof hatches and accessories, PVC roofing membrane, sheet metal roof flashings, aluminum interior storefronts install, and sound insulation at interior walls
Site: Upcoming work includes the finishes – paint, tile, shade covers, etc.
Construction for the Career Technical project continues and is approximately 58% complete!
July 2013 Progress Update
Work Completed
Building 3100: Work completed for this month included roll up coiling doors installation
Building 3200: Work completed for this month included the steel framing for roof equipment, roof drains, skylight curbs, framing interior walls, hollow metal door frames, and exterior masonry sealer
Site: Work completed for this month included the mechanical yard footings and masonry walls and columns
Work In Progress
Building 3100: Work in progress includes steel framing for roof equipment, metal roof decking, framing interior walls, hollow metal door frames installation, ceilings and soffits framing, and exterior sealer
Building 3200: Work in progress includes metal decking at roof, MEP sleeves through roof and hangers, fire sprinkler installation, HVAC rough-in above ceiling (wet and dry), electric above ceiling, and MEP wall and soffit rough-in
Site: Work in progress includes the structural steel for shade structures
Upcoming Work
Building 3100: Upcoming work includes MEP sleeves through roof and hangers, installing roof drains, set mechanical curbs at roof, roof hatches and accessories, skylight curbs installation, and fire sprinkler system installation
Building 3200: Upcoming work includes setting mechanical curbs at roof, roof hatches and accessories, PVC roofing membrane, and exterior window installation and glazing
Site: Upcoming work includes the finishes – paint, tile, shade covers, etc. and mechanical equipment and piping installation
The modernization of the 900 building is underway to support the campus's business and data processing needs. The improvements will include new architectural finishes, new HVAC and electrical systems.
Construction commenced in May 2013 and has achieved 92% participation from local contractors! The project is scheduled to be completed by November 2013.
As part of the Imperial Valley College Foundation's K-12 tour, Dr. Jim Fisher's chemistry students hosted a tour of the new science building with Calexico elementary students from Mains Elementary School.
"Best tour ever!"; "I wanna come to school here!"; "That was really cool"; were all phrases heard from the 5th grade classes from Mains Elementary school in Calexico as they concluded the tour.
The project includes new construction trade labs and modernization of existing 1100, 1200, and 1300 buildings to include lab classrooms for computers, electronics, construction, HVAC, welding, engineering, public safety, etc.
Project features for the new buildings include:
3100 Building
3200 Building
The College proudly achieved approximately 72% participation from local subcontractors for the Career Technical project due to effective outreach efforts including ongoing workshops and outreach events to educate and support local subcontractors increasing their participation in the project.
Construction is in progress and is scheduled to be completed by March 2014.
February 2013 Construction Progress:
WORK COMPLETED:
Building 3100: Work completed for this month included 2nd lift masonry walls
Building 3200: Work completed for this month included setting structural steel roof beams, grade, form rebar, and pour slab on grade
Site: Work completed for this month included fire line service and hydrants, and activate site system
WORK IN PROGRESS:
Building 3100: Work in progress includes electrical rough-in masonry walls, 3rd lift masonry walls, plumbing under slab on grade
Building 3200: Work in progress includes wall furring
Site: Work in progress includes the communications data and vaults and fire alarm
UPCOMING WORK:
Building 3100: Upcoming work includes setting the structural roof beams, and setting the steel trusses
Building 3200: Upcoming work includes setting the steel trusses, install metal decking at roof, MEP sleeves through roof and hangers, install roof drains, MEP and fire sprinkler, install beam clamps and hangers
Site: Upcoming work includes underground utilities/stub-out (wet and dry)
February 2013 Construction Progress Photos:
Citizens Oversight Committee to meet Thursday, March 21, 2013 at 12 noon, IVC Board Room
Citizens Oversight Committee to meet Thursday, September 27, 2012
12pm – IVC Board Room
Contact:Bill GayDirector of Media& Community Relations(760) 335-6124 | For Immediate ReleaseDecember 8, 2011 |
Groundbreaking to be held Friday, December 16th 10:30 am IVC Main Campus, NW Parking Lot H
Career Technical Education Facilities Site Plan and Elevation
IMPERIAL, CA—The design efforts for the Imperial Valley College's (IVC) New Career Technical Education Facilities are well underway. The community's support of Measure "J" has helped bring this project to a reality.
Measure "J" is an $80 million bond authorization that was approved by voters in November 2010 to improve education and expand career opportunities.
The project includes the construction of a new Career Technical Education Building and modernization of existing 1100, 1200, and 1300 buildings. The project has been submitted to the Division of State Architect (DSA) for review and construction is scheduled to start in Spring 2012.
The new Career Technical Education Building will house the expanded curriculum covering Administration of Justice * Building Construction * Correctional Science * Electrical Wiring * Electronics * Emergency Medical Technology * Fire Technology * Peace Officer Standards Training * Solar Energy * Welding Technology *.
IVC's construction team has commenced a series of subcontractor outreach meetings to encourage local participation on this project. Additional subcontractor outreach events will be held in December at the Pioneer Museum . The next event will take place on:
Friday, December 9, 2011 – 11:00am – 2:00pmInsurance/Bonding/Prevailing WageExperts in Bonding, Insurance and Prevailing Wage will speak to various types of insurance products, how to establish or increase a business's bonding capacity, and review of Prevailing Wage processes.For further information or to answer any additional questions, please contact Bill Gay, Director of Media & Community Relations at (760) 355-6124.
Contact:Bill GayDirector of Media& Community Relations(760) 335-6124 | For Immediate ReleaseNovember 8, 2011 |
IMPERIAL, CA—Imperial Valley College will be holding a series of workshops over the next several weeks to educate local subcontractors with an objective of increasing their participation in upcoming IVC construction projects.
"The Board of Trustees of the Imperial Valley College (IVC) is committed to hiring local firms to work on Measure "J" construction projects," said IVC Vice President for Business Services John Lau. "This is following through on our commitment to the Valley to facilitate more local firms to be successful in the bidding process.
Measure "J" is an $80 million bond authorization that was approved by voters in November 2010 to improve education and expand career opportunities.
IVC has selected Nielsen Construction Ca. to provide Lease-Leaseback services for the bond program. Nielsen Construction Ca. will be holding a series of subcontractor outreach meetings. All meetings will be held at the Pioneer Museum:
During the meetings, IVC and Nielsen Construction Co. will review Nielsen's role in the process, the project scope, and prequalification materials and requirements.
In addition, Building Information Modeling (BIM) seminars will be held to educate the local contracting community on the software's use and benefits. BIM is a computer software tool that enables the coordination of building systems design and installation and analyses building efficiency and lifecycle costs. The software enables all team members to visualize and coordinate a project in 3-D as opposed to 2-D plans resulting in more cost effective and high quality projects. This tool has resulted in substantial savings in cost and time.
Experts in Bonding, Insurance and Prevailing Wage will also participate in leading several of these Outreach Events. They will cover various types of insurance products, how to establish or increase a business's bonding capacity, and review of Prevailing Wage processing.
For further information or to answer any additional questions regarding the scheduled outreach events, please contact Bill Gay, Director of Media & Community Relations at (760) 355-6124.
The Imperial Valley College Measure L and Measure J Oversight Committee is excited to provide a brand new website to inform the IVC community about the progress of new construction and modernization on campus. Measure L and J were authorized by the voters of IVC to provide greater opportunities for students seeking career education and vocational training in our community.