Archived News

Thank you to all who attended the Ribbon Cutting Ceremony for the two new Career Technical Education Buildings to be open mid-June.

More pictures can be found at: http://gallery.imperial.edu/CTE-Buildings-Ribbon-Cutting-Ceremony


cte ribbon_cutting_ceremony

IMG_6280

thumb IMG_6401

thumb_A013615

thumb _A013690

thumb _A013696

thumb _A013698

thumb _B012002

All bond funds have been expended.  The next Citizens Bond Oversight Committee meeting is TBA.

20131101_124727_resized-1024x575.jpg
20131104_134829_resized-1024x575.jpg
20131105_080251_resized-1024x575.jpg
20131106_121518_resized-1024x575.jpg
20131107_075027_resized_1-1024x575.jpg
20131108_113245_resized-1024x575.jpg
20131112_124228_resized-1024x575.jpg
20131113_081533_resized-1024x575.jpg
20131114_131535_resized-1024x575.jpg
20131115_101034_resized-1024x575.jpg
20131118_080424_resized-1024x575.jpg
20131119_071404_resized-1024x575.jpg
20131120_075735_resized-1024x575.jpg
20131121_112754_resized-1024x575.jpg
20131122_112830_resized-1024x575.jpg
20131122_123107_resized-1024x575.jpg
20131125_080538_resized-1024x575.jpg
20131125_115739_resized-1024x575.jpg
20131126_132522_resized-1024x575.jpg
20131126_132540_resized-1024x575.jpg
20131127_123308_resized-1024x575.jpg
20131127_142033_resized-1024x575.jpg
20131202-1024x575.jpg
20131203-1024x575.jpg

 

Construction for the Career Technical Facilities project continues and is approximately 81% complete!

November 2013 Progress Update

Work Completed

Building 3100: Work completed for this month included the fire sprinkler installation, HVAC rough-in (above ceilings) wet and dry, and hangin drywall walls and ceilings

Building 3200: Work completed for this month included the aluminum interior storefronts installation and tape/texturing walls and ceilings

Work in Progress

Building 3100: Work in progress includes the aluminum storefronts installation, storefront glazing, and taping/texturing walls

Building 3200: Work in progress includes the storefront glazing and paint interior walls and ceiling

Site: Work in progress includes concrete work  – grade, form, rebar, and pour

Upcoming Work

Building 3100: Upcoming work includes the painting of the interior walls and ceilings

Building 3200: Upcoming work includes ceramic tile at the toilet rooms, T-bar ceiling grid work, display cases at entrances, cabinets and millwork, electrical ceiling fixtures and trim, mechanical ceiling fixtures, plumbing fixtures and finishes, and miscallenous exterior finishes

Site: Upcoming work includes the mechanical equipment and piping installation, asphalt paving of the road, and sleeves for irrigation under concrete

 

20130801_070235_resized-1024x575.jpg
20130801_070252_resized-1024x575.jpg
20130802_065302_resized-1024x575.jpg
20130802_072402_resized-1024x575.jpg
20130805_080317_resized-1024x575.jpg
20130805_080524_resized-1024x575.jpg
20130806_070928_resized-1024x575.jpg
20130806_084438_resized-1024x575.jpg
20130807_064258_resized-1024x575.jpg
20130807_084811_resized-1024x575.jpg
20130808_072501_resized-1024x575.jpg
20130808_132320_resized-1024x575.jpg
20130819_092543_resized-1024x575.jpg
20130820_073036_resized-1024x575.jpg
20130821_090934_resized-1024x575.jpg
20130822_065614_resized-1024x575.jpg
20130823_091502_resized-1024x575.jpg
20130826_122011_resized-1024x575.jpg
20130827_123433_resized-1024x575.jpg
20130828_065515_resized-1024x575.jpg
20130829_090248_resized-1024x575.jpg
20130830_094027_resized-1024x575.jpg
20130903_085153_resized.jpg
20130904_121402_resized.jpg

Construction for the Career Technical Facilities project continues and is approximately  63% complete!

August 2013 Progress Update

Work Completed

Building 3100:  Work completed for this month included steel framing roof equipment, metal roof decking, MEP sleeves through roof and hangers, tubular skylight curbs installation, frame interior walls, and exterior sealer

Building 3200:  Work completed for this month included the metal decking at the roof, MEP sleeves through roof and hangers, fire sprinkler installation, MEP wall and soffit rough-in

Site:  Work completed for this month included the structural steel for shade structures

Work In Progress

Building 3100:  Work in progress includes installing the roof drains, fire sprinkler installation, hollow metal door frames installation, MEP rough-in at walls and soffit, and ceilings and soffit framing

Building 3200:  Work in progress includes setting mechanical curbs at roof, exterior window installation and glazing, HVAC rough-in above ceiling – wet and dry, and electrical rough-in above ceiling

Upcoming Work

Building 3100:  Upcoming work includes setting mechanical curbs at roof, roof hatches and accessories, PVC membrane roofing, sheet metal flashings, exterior windows installation and glazing, and set HVAC roof equipment

Building 3200:  Upcoming work includes roof hatches and accessories, PVC roofing membrane, sheet metal roof flashings, aluminum interior storefronts install, and sound insulation at interior walls

Site:  Upcoming work includes the finishes – paint, tile, shade covers, etc.

20130701_074421_resized.jpg
20130702_072439_resized.jpg
20130703_075609_resized.jpg
20130705_103219_resized.jpg
20130708_094854_resized.jpg
20130709_080943_resized.jpg
20130710_113738_resized-1024x575.jpg
20130711_124440_resized-1024x575.jpg
20130712_125213_resized-1024x575.jpg
20130715_063202_resized-1024x575.jpg
20130716_114020_resized-1024x575.jpg
20130717_073846_resized-1024x575.jpg
20130718_081616_resized-1024x575.jpg
20130719_080603_resized-1024x575.jpg
20130722_063257_resized-1024x575.jpg
20130723_093427_resized-1024x575.jpg
20130724_064719_resized-1024x575.jpg
20130725_122925_resized-1024x575.jpg
20130726_074806_resized-1024x575.jpg
20130729_072237_resized-1024x575.jpg
20130730_085006_resized-1024x575.jpg
20130731_124001_resized-1024x575.jpg
20130801_070235_resized-1024x575.jpg
20130802_065302_resized-1024x575.jpg

Construction for the Career Technical project continues and is approximately 58% complete!

July 2013 Progress Update

Work Completed

Building 3100: Work completed for this month included roll up coiling doors installation

Building 3200: Work completed for this month included the steel framing for roof equipment, roof drains, skylight curbs, framing interior walls, hollow metal door frames, and exterior masonry sealer

Site: Work completed for this month included the mechanical yard footings and masonry walls and columns

Work In Progress

Building 3100: Work in progress includes steel framing for roof equipment, metal roof decking, framing interior walls, hollow metal door frames installation, ceilings and soffits framing, and exterior sealer

Building 3200: Work in progress includes metal decking at roof, MEP sleeves through roof and hangers, fire sprinkler installation, HVAC rough-in above ceiling (wet and dry), electric above ceiling, and MEP wall and soffit rough-in

Site: Work in progress includes the structural steel for shade structures

Upcoming Work

Building 3100: Upcoming work includes MEP sleeves through roof and hangers, installing roof drains, set mechanical curbs at roof, roof hatches and accessories, skylight curbs installation, and fire sprinkler system installation

Building 3200: Upcoming work includes setting mechanical curbs at roof, roof hatches and accessories, PVC roofing membrane, and exterior window installation and glazing

Site: Upcoming work includes the finishes – paint, tile, shade covers, etc. and mechanical equipment and piping installation

 

The modernization of the 900 building is underway to support the campus's business and data processing needs. The improvements will include new architectural finishes, new HVAC and electrical systems.

Construction commenced in May 2013 and has achieved 92% participation from local contractors! The project is scheduled to be completed by November 2013.

As part of the Imperial Valley College Foundation's K-12 tour, Dr. Jim Fisher's chemistry students hosted a tour of the new science building with Calexico elementary students from Mains Elementary School. 

 "Best tour ever!"; "I wanna come to school here!";  "That was really cool";  were all phrases heard from the 5th grade classes from Mains Elementary school in Calexico as they concluded the tour. 

 science-tour-1

science-tour-2

science-tour-3

 

The project includes new construction trade labs and modernization of existing 1100, 1200, and 1300 buildings to include lab classrooms for computers, electronics, construction, HVAC, welding, engineering, public safety, etc.

Project features for the new buildings include:

3100 Building

  • (2) smart classrooms
  • (3) construction trade labs
  • (1) welding lab
  • (1) renewable energy lab
  • (1) electronics lab
  • (1) computer lab

3200 Building

  • (2) Police Officer Standard Training and Fire Academy Lab
  • (1) Emergency Medical Services Lab
  • (2) smart classrooms
thumb CTE-Design-Rendering

3100 & 3200 Buildings – Design Rendering

The College proudly achieved approximately 72% participation from local subcontractors for the Career Technical project due to effective outreach efforts including ongoing workshops and outreach events to educate and support local subcontractors increasing their participation in the project.

Construction is in progress and is scheduled to be completed by March 2014.

 February 2013 Construction Progress:

WORK COMPLETED:

Building 3100: Work completed for this month included 2nd lift masonry walls

Building 3200: Work completed for this month included setting structural steel roof beams, grade, form rebar, and pour slab on grade

Site: Work completed for this month included fire line service and hydrants, and activate site system

WORK IN PROGRESS:

Building 3100: Work in progress includes electrical rough-in masonry walls, 3rd lift masonry walls, plumbing under slab on grade

Building 3200: Work in progress includes wall furring

Site: Work in progress includes the communications data and vaults and fire alarm

UPCOMING WORK:

Building 3100: Upcoming work includes setting the structural roof beams, and setting the steel trusses

Building 3200: Upcoming work includes setting the steel trusses, install metal decking at roof, MEP sleeves through roof and hangers, install roof drains, MEP and fire sprinkler, install beam clamps and hangers

Site: Upcoming work includes underground utilities/stub-out (wet and dry)

February 2013 Construction Progress Photos:

20130225_080310-1024x768.jpg
20130226_134254-1024x768.jpg
20130228_085707_resized.jpg
20130228_093347_resized.jpg
DSC03069.jpg
DSC03074.jpg
DSC03080.jpg
DSC03086.jpg
DSC03097.jpg
DSC03099.jpg
DSC03103.jpg
DSC03108.jpg
DSC03111.jpg
DSC03125.jpg
DSC03131.jpg
DSC03132.jpg
DSC03136.jpg
DSC03137.jpg
DSC03146.jpg
DSC03149.jpg
DSC03150.jpg
DSC03152.jpg

 

Citizens Oversight Committee to meet Thursday, March 21, 2013 at 12 noon, IVC Board Room

A look at completed and planned projects with Measure L &J…

thumb IVC-Master-Plan_3.12.13

Citizens Oversight Committee to meet Thursday, September 27, 2012

12pm – IVC Board Room

 

IVC-Logo

Contact:
Bill Gay
Director of Media
& Community Relations
(760) 335-6124
For Immediate Release
December 8, 2011

PRESS RELEASE

NEW CAREER TECHNICAL EDUCATIONAL FACILITIES DESIGN WELL UNDER WAY

Groundbreaking to be held Friday, December 16th 10:30 am IVC Main Campus, NW Parking Lot H

thumb Career-Tech-Building thumb Career-Tech-Map3

Career Technical Education Facilities Site Plan and Elevation

IMPERIAL, CA—The design efforts for the Imperial Valley College's (IVC) New Career Technical Education Facilities are well underway. The community's support of Measure "J" has helped bring this project to a reality.

Measure "J" is an $80 million bond authorization that was approved by voters in November 2010 to improve education and expand career opportunities.

The project includes the construction of a new Career Technical Education Building and modernization of existing 1100, 1200, and 1300 buildings. The project has been submitted to the Division of State Architect (DSA) for review and construction is scheduled to start in Spring 2012.

The new Career Technical Education Building will house the expanded curriculum covering Administration of Justice * Building Construction * Correctional Science * Electrical Wiring * Electronics * Emergency Medical Technology * Fire Technology * Peace Officer Standards Training * Solar Energy * Welding Technology *.

IVC's construction team has commenced a series of subcontractor outreach meetings to encourage local participation on this project. Additional subcontractor outreach events will be held in December at the Pioneer Museum . The next event will take place on:

Friday, December 9, 2011 – 11:00am – 2:00pm
Insurance/Bonding/Prevailing Wage
Experts in Bonding, Insurance and Prevailing Wage will speak to various types of insurance products, how to establish or increase a business's bonding capacity, and review of Prevailing Wage processes.

For further information or to answer any additional questions, please contact Bill Gay, Director of Media & Community Relations at (760) 355-6124.

 


IVC-LogoNielsenCC Logo_Color800px

Contact:
Bill Gay
Director of Media
& Community Relations
(760) 335-6124
For Immediate Release
November 8, 2011

PRESS RELEASE

IVC CONSTRUCTION TEAM TO HOLD LOCAL SUBCONTRACTOR OUTREACH MEETINGS

IMPERIAL, CA—Imperial Valley College will be holding a series of workshops over the next several weeks to educate local subcontractors with an objective of increasing their participation in upcoming IVC construction projects.

"The Board of Trustees of the Imperial Valley College (IVC) is committed to hiring local firms to work on Measure "J" construction projects," said IVC Vice President for Business Services John Lau. "This is following through on our commitment to the Valley to facilitate more local firms to be successful in the bidding process.

Measure "J" is an $80 million bond authorization that was approved by voters in November 2010 to improve education and expand career opportunities.

IVC has selected Nielsen Construction Ca. to provide Lease-Leaseback services for the bond program.  Nielsen Construction Ca. will be holding a series of subcontractor outreach meetings.  All meetings will be held at the Pioneer Museum:

  • Wednesday – November 16, 2011 – BBQ –  10:00am to 3:00pm
    • Bond Program, Career Tech Description, Bidding and Construction Timelines
  • Wednesday – November 30, 2011 – 10:00am to 3:00pm (all day event)
    • BIM Seminar
  • Friday, December 9, 2011 – 10:00am to 3:00pm (all day event)
    • Insurance/Bonding/Prevailing Wage
  • Friday, December 16, 2011 – 10:00am to 3:00pm (all day event)
    • Recap and Q&A
    • Insurance/Bonding/Prevailing Wage/BIM Seminar

During the meetings, IVC and Nielsen Construction Co. will review Nielsen's role in the process, the project scope, and prequalification materials and requirements.

In addition, Building Information Modeling (BIM) seminars will be held to educate the local contracting community on the software's use and benefits.  BIM is a computer software tool that enables the coordination of building systems design and installation and analyses building efficiency and lifecycle costs.  The software enables all team members to visualize and coordinate a project in 3-D as opposed to 2-D plans resulting in more cost effective and high quality projects.  This tool has resulted in substantial savings in cost and time.

Experts in Bonding, Insurance and Prevailing Wage will also participate in leading several of these Outreach Events.  They will cover various types of insurance products, how to establish or increase a business's bonding capacity, and review of Prevailing Wage processing.

For further information or to answer any additional questions regarding the scheduled outreach events, please contact Bill Gay, Director of Media & Community Relations at (760) 355-6124.

The Imperial Valley College Measure L and Measure J Oversight Committee is excited to provide a brand new website to inform the IVC community about the progress of new construction and modernization on campus. Measure L and J were authorized by the voters of IVC to provide greater opportunities for students seeking career education and vocational training in our community.