20130801_070235_resized-1024x575.jpg
20130801_070252_resized-1024x575.jpg
20130802_065302_resized-1024x575.jpg
20130802_072402_resized-1024x575.jpg
20130805_080317_resized-1024x575.jpg
20130805_080524_resized-1024x575.jpg
20130806_070928_resized-1024x575.jpg
20130806_084438_resized-1024x575.jpg
20130807_064258_resized-1024x575.jpg
20130807_084811_resized-1024x575.jpg
20130808_072501_resized-1024x575.jpg
20130808_132320_resized-1024x575.jpg
20130819_092543_resized-1024x575.jpg
20130820_073036_resized-1024x575.jpg
20130821_090934_resized-1024x575.jpg
20130822_065614_resized-1024x575.jpg
20130823_091502_resized-1024x575.jpg
20130826_122011_resized-1024x575.jpg
20130827_123433_resized-1024x575.jpg
20130828_065515_resized-1024x575.jpg
20130829_090248_resized-1024x575.jpg
20130830_094027_resized-1024x575.jpg
20130903_085153_resized.jpg
20130904_121402_resized.jpg

Construction for the Career Technical Facilities project continues and is approximately  63% complete!

August 2013 Progress Update

Work Completed

Building 3100:  Work completed for this month included steel framing roof equipment, metal roof decking, MEP sleeves through roof and hangers, tubular skylight curbs installation, frame interior walls, and exterior sealer

Building 3200:  Work completed for this month included the metal decking at the roof, MEP sleeves through roof and hangers, fire sprinkler installation, MEP wall and soffit rough-in

Site:  Work completed for this month included the structural steel for shade structures

Work In Progress

Building 3100:  Work in progress includes installing the roof drains, fire sprinkler installation, hollow metal door frames installation, MEP rough-in at walls and soffit, and ceilings and soffit framing

Building 3200:  Work in progress includes setting mechanical curbs at roof, exterior window installation and glazing, HVAC rough-in above ceiling – wet and dry, and electrical rough-in above ceiling

Upcoming Work

Building 3100:  Upcoming work includes setting mechanical curbs at roof, roof hatches and accessories, PVC membrane roofing, sheet metal flashings, exterior windows installation and glazing, and set HVAC roof equipment

Building 3200:  Upcoming work includes roof hatches and accessories, PVC roofing membrane, sheet metal roof flashings, aluminum interior storefronts install, and sound insulation at interior walls

Site:  Upcoming work includes the finishes – paint, tile, shade covers, etc.