20130701_074421_resized.jpg
20130702_072439_resized.jpg
20130703_075609_resized.jpg
20130705_103219_resized.jpg
20130708_094854_resized.jpg
20130709_080943_resized.jpg
20130710_113738_resized-1024x575.jpg
20130711_124440_resized-1024x575.jpg
20130712_125213_resized-1024x575.jpg
20130715_063202_resized-1024x575.jpg
20130716_114020_resized-1024x575.jpg
20130717_073846_resized-1024x575.jpg
20130718_081616_resized-1024x575.jpg
20130719_080603_resized-1024x575.jpg
20130722_063257_resized-1024x575.jpg
20130723_093427_resized-1024x575.jpg
20130724_064719_resized-1024x575.jpg
20130725_122925_resized-1024x575.jpg
20130726_074806_resized-1024x575.jpg
20130729_072237_resized-1024x575.jpg
20130730_085006_resized-1024x575.jpg
20130731_124001_resized-1024x575.jpg
20130801_070235_resized-1024x575.jpg
20130802_065302_resized-1024x575.jpg

Construction for the Career Technical project continues and is approximately 58% complete!

July 2013 Progress Update

Work Completed

Building 3100: Work completed for this month included roll up coiling doors installation

Building 3200: Work completed for this month included the steel framing for roof equipment, roof drains, skylight curbs, framing interior walls, hollow metal door frames, and exterior masonry sealer

Site: Work completed for this month included the mechanical yard footings and masonry walls and columns

Work In Progress

Building 3100: Work in progress includes steel framing for roof equipment, metal roof decking, framing interior walls, hollow metal door frames installation, ceilings and soffits framing, and exterior sealer

Building 3200: Work in progress includes metal decking at roof, MEP sleeves through roof and hangers, fire sprinkler installation, HVAC rough-in above ceiling (wet and dry), electric above ceiling, and MEP wall and soffit rough-in

Site: Work in progress includes the structural steel for shade structures

Upcoming Work

Building 3100: Upcoming work includes MEP sleeves through roof and hangers, installing roof drains, set mechanical curbs at roof, roof hatches and accessories, skylight curbs installation, and fire sprinkler system installation

Building 3200: Upcoming work includes setting mechanical curbs at roof, roof hatches and accessories, PVC roofing membrane, and exterior window installation and glazing

Site: Upcoming work includes the finishes – paint, tile, shade covers, etc. and mechanical equipment and piping installation