Construction for the Career Technical project continues and is approximately 58% complete!
July 2013 Progress Update
Work Completed
Building 3100: Work completed for this month included roll up coiling doors installation
Building 3200: Work completed for this month included the steel framing for roof equipment, roof drains, skylight curbs, framing interior walls, hollow metal door frames, and exterior masonry sealer
Site: Work completed for this month included the mechanical yard footings and masonry walls and columns
Work In Progress
Building 3100: Work in progress includes steel framing for roof equipment, metal roof decking, framing interior walls, hollow metal door frames installation, ceilings and soffits framing, and exterior sealer
Building 3200: Work in progress includes metal decking at roof, MEP sleeves through roof and hangers, fire sprinkler installation, HVAC rough-in above ceiling (wet and dry), electric above ceiling, and MEP wall and soffit rough-in
Site: Work in progress includes the structural steel for shade structures
Upcoming Work
Building 3100: Upcoming work includes MEP sleeves through roof and hangers, installing roof drains, set mechanical curbs at roof, roof hatches and accessories, skylight curbs installation, and fire sprinkler system installation
Building 3200: Upcoming work includes setting mechanical curbs at roof, roof hatches and accessories, PVC roofing membrane, and exterior window installation and glazing
Site: Upcoming work includes the finishes – paint, tile, shade covers, etc. and mechanical equipment and piping installation